UPDATE ON THE LORAIN AVENUE REHABILITATION CONSTRUCTION PROJECT, IN CLEVELAND, OHIO, AS OF APRIL 3, 2015

Submitted by Satinder P S Puri on Sat, 04/04/2015 - 23:34.
 
 
 
UPDATE ON THE LORAIN AVENUE REHABILITATION CONSTRUCTION PROJECT IN CLEVELAND,OHIO, AS OF APRIL 3, 2015
 
PROJECT: The 1.8 mile long project from West 150th Street to West 117th Street, with a construction cost of $8.3 million, will pass through three wards on Cleveland’s West Side: 17, 16, and 11.
 
The work will include pavement rehabilitation, new  -- curbs, sidewalks, and driveway aprons, replacement of existing catch basins, additional catch basins, and ADA (American Disabilities Act) compliant ramps.
 
Streetscape amenities will include decorative colored and stamped concrete amenity strips, trees, pole consolidation, and trash receptacles.
 
About 80 poles will be consolidated. But the project will continue to be littered with poles – a big eyesore.
 
Traffic signal systems at West 143rd. 140th, Fairwood/138th, 130th, and 125th will be upgraded.
 
Traffic signals at West 134th, 134th/Berea. and 120th will be removed because of low traffic volume.
 
The roadway will include one 12 ft. through lane each way and one two way 10 ft. left turn lane. There will be exclusive bike lanes (5 ft. or 6 ft.) for the most part and sharrows where exclusive lanes are not possible. Parking, where possible, will be provided on the north side.
 
CONSTRUCTION SCHEDULE: 
Start March 9, 2015. 
In 2015: Work from West 117th to West 140th.
In 2016: Work from West 140th to West 150th.
Completion date: November 15, 2016.
 
MAINTENANCE OF TRAFFIC:
The 54 ft. wide roadway will be divided as follows:
Left to Right: 12 ft. Lane going West, 11 ft. Lane going East, 
4 ft. Barrel Zone, 27 ft. Work Zone. 
The pattern will flip where the work zone is on the north side.
 
LIFE-SPAN: The rehabilitated pavement is expected to have a life-span of 7-10 years.
 
DOMINION EAST: Will be working on upgrading their gas lines simultaneously with the roadway project. 
 
CONTACTING COUNCILMAN BRIAN KAZY:
Mr. Kazy wants residents from Ward 16 to contact him with their concerns for the project.
Office: (216) 664-2942
Home (216) 251-2331
E-mail: bkazy [at] clevelandcitycouncil [dot] org
 
CONTRACTOR’S TRAILER:
Located on West 150th Street
 
PROJECT CONTACTS:
Field Office: Darrell Dunnican (216) 244-1242
City Hall Office: Frank Keehl, Consulting Engineer, Mayor’s Office of Capital Projects, (216) 664-2256
 
UPDATE AS OF APRIL 3, 2015:
See attached photographs, arranged sequentially.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
REFERENCES:
See previous posts on REALNEO
02-28-15: REPORT ON THE PUBLIC MEETING ON THE LORAIN AVENUE REHABILITATION CONSTRUCTION PROJECT
 
AttachmentSize
Slide1.JPG55.65 KB
Slide2.JPG69.57 KB
Slide3.JPG48.04 KB
Slide4.JPG70.49 KB
Slide5.JPG55.79 KB
Slide6.JPG70.62 KB
Slide7.JPG63.69 KB
Slide8.JPG51.82 KB
Slide9.JPG70.21 KB
Slide10.JPG60.55 KB
Slide11.JPG75.88 KB
Slide12.JPG60.06 KB
Slide13.JPG62.36 KB
Slide14.JPG58.75 KB
Slide15.JPG65.09 KB
Slide16.JPG60.03 KB
Slide17.JPG54.19 KB
Slide18.JPG60.89 KB
Slide19.JPG60.49 KB
Slide20.JPG49.04 KB
Slide21.JPG51.41 KB
Slide22.JPG64.88 KB
Slide23.JPG50.54 KB
Slide24.JPG54.06 KB
Slide25.JPG55.98 KB
Slide26.JPG56.79 KB
Slide27.JPG65.47 KB
Slide28.JPG55.02 KB
Slide29.JPG56.53 KB
Slide30.JPG60.36 KB
Slide31.JPG53.54 KB
Slide32.JPG63.13 KB
Slide33.JPG56.43 KB
Slide34.JPG61.1 KB
( categories: )